On October 10, the first overseas EPC new energy project undertaken by PowerChina Hydropower Seventh Engineering Bureau, the 64MW Tanavan PV Power Station (T Station) and the 64MW Malagon East PV Power Station (M Station) under the T&M PV Power Station, completed the one-time reverse power commissioning, marking that the project is about to be connected to the grid and put into commercial operation.
Since October 1, the Tanavan PV Power Station has taken the lead in starting the reverse power commissioning; On October 10, the Malagon East PV Power Station started the reverse power commissioning. To ensure the success of the commissioning, all members of the project department stick to their posts, go all out to carry out rectification and rectification, and complete the reverse power work with high quality, which is highly praised by the owner.
So far, all 7 sites of the Tanavan PV Power Station have been connected to the grid, and a total of 400,000 kWh of clean energy electricity has been transmitted to the outside world, injecting strong momentum into local sustainable development. At the same time, the Malagon East PV Power Station is ready to start the site grid-connected power generation.